COMMISSIONERS PRESENT: Chairperson Jim Tuttle; Tom Herlihy & Charlie
McGettigan.
CLERK: Diane Nilsson
AUDIENCE PRESENT: Ken Sullivan
Jim Tuttle called the meeting to order at 7:42 p.m.
Minutes - August 28, 2002
MOTION: Mr. McGettigan moved to approve the 8/28/02 minutes as written.
Mr. Herlihy seconded and
all were in favor.
Old Business
1. Tom Quinn gravel operation next to WWW recharge area: Mr.
Quinn still doing research. Will contact the
board when ready to be on agenda again.
2. Ken Sullivan Water Service Installation Bill: Mr. Sullivan
said that he was pleased with the work that the water dept. did on his
installation and with the speed with which it was done. He did feel that
the cost of the
installation was exceedingly high though. He specifically felt that
it is unfair for one water user to pay almost nothing for an installation,
if they are close to the water main, and for another user to pay thousands
because they are farther from the main. The board explained that at this
point in time, users are charged time and materials for any installation
and because of the location of the water mains, some installations will
be more
expensive than others. In the future, the board may consider changing
this policy in some way.
3. Status of Sam Proctor, Jr. Installations: Water line easement
deed still not complete. In addition, a letter needs to be sent to Mr.
Proctor reminding him that the financial obligation of the water dept.
for the shut-off and the water meter installations, at 40 Madison Street,
end at the street, except that the water dept. will supply the meter at
no charge. Mr. Proctor is responsible for contracting and installing the
shut-off and water meter, pursuant to the standard practices of the Town
of Wilton Water Commissioners. Attorney Little will be asked to
draft letter by Mr. McGettigan.
4. Status of current water projects & to do list:
Repair valves & leaks @ new reservoir. DONE
Trees cut @ new reservoir. Not complete. Mr. Tuttle
will hire Chappel Farms to do the work.
Dam maintenance @ new reservoir. DONE
Fence project @ new reservoir. Not complete.
Cornerstone Paint Co. references. Postponed until
spring. Ms. Nilsson to write letters to be sent to all bidders.
Second River Crossing: Mr. McGettigan spoke to
George Thayer of Guilford Transportation about the request to bring the
water under the RR via directional drilling. Mr. Thayer
said that he would consider it only if a 32 sleeve was put in place prior
to the drilling. Mr. McGettigan contacted John @ Bobs Directional Drilling
and asked him to come up with a price for doing the drilling this way.
Tom will contact VP of Engineering @ Guilford and try to resolve RR/boring
issue.
Capital Reserve Account for Second River Crossing:
Not done. Tom will email Barry Greene to set it up.
Bill Town for materials used in police station
water installation. Not done. Mr. McGettigan will complete.
Contact Jaffrey re: Holt Road loop. DONE. They
are not interested in the job.
Clean up debris on Glines property/resolve boundary
dispute. Not done. No response from Mr. Glines so will drop from old business.
Replace & relocate hydrant on Russell Street.
Not done.
Replace & relocate hydrant on Intervale Road.
Not done.
Install 6 gate in main line @ Dale & Laurel
Hill Street. Not done.
5. Discussion of security issues re: wells, pump station &
standpipe. There was no discussion.
6. Letter of Deficiency for Stockwell Brook Dam from DES. There
are a couple of things remaining to fix
including the leak @ the base of the dam.
New Business
1. Emergency plan for wells, pump house & tank due @ end of
year. Mr. Herlihy will work on this.
2. Mr. Herlihy reported that the brush around the tank will be
cut next week.
3. Mr. Tuttle said that the tank is due for inspection in 2003.
It was last inspected in 1998. The cost for cleaning
and inspection of the tank and the welds is $2,375. For an additional
$300 the company will remove up to 6 of
sediment. The company is Underwater Solutions of Matapoisit, MA and
they did the previous inspection.
The meeting was adjourned at 10:15 p.m.
Respectfully submitted,
Diane Nilsson, Clerk
Posted: 10/29/02
ACTION ITEMS
Charlie McGettigan
Contact Attorney Little regarding Sam Proctor easement language &
financial responsibility issues.
Find out what $2,400 charge from Efficiency Production, Inc. in the
new equipment line item was for.
Bill the Town for materials used for Police Station water line installation.
Complete fence project at new reservoir.
Replace and relocate hydrant on Russell Street.
Replace and relocate hydrant on Intervale Road.
Install 6 gate in main line at Dale & Laurel Hill Street.
Tom Herlihy
Email Barry Greene re: opening Capital Reserve Acct. for Second River
Crossing.
Contact Guilford VP of Engineering to try to resolve RR/boring issue.
Work on Emergency Plan.
Jim Tuttle
Complete tree removal @ new reservoir with Chappel Farms
FUTURE PROJECTS
Come up with revised rules & regs after reviewing those of Milford,
Merrimack, Peterborough & Greenville. These to include standardized
costs for bringing new service to residences and businesses as well as
costs for meter installations, among other things.
Paint standpipe
Holt Road loop project